Construction Progress - 28 March
- Dormitory
Floor carpet work at the lounge of the ground floor has been completed. The internal staircase, w...
Construction Progress - 28 March
Floor carpet work at the lounge of the ground floor has been completed. The internal staircase, w...
Construction Progress - 21 March
Wall and floor finishes on the ground floor are in progress in various areas. The first photo sho...
Japanese Language Classes at NIC
‘Do I need to speak Japanese in order to apply to your school?’ This is one recurrent question fr...
Construction Progress - 14 March 2022
Today, the floor finishing work of the dining room on the first floor just started. The flooring ...
Construction Progress - 7 March 2022
The installation of the glass eaves at the entrance is now complete. On the second floor, the wal...